Project PassportBW-NS-0142Illustrative example

Construction of 2-classroom block

[Community], [LGA], Niger State Education Capital project 2025 budget
Ask Clara about this project
Budgeted
₦36,750,000
2025 capital budget, education sector
Implemented by
[Institution]
As named in the budget record
Contract
Not yet public
Award documents requested
Location
Verified
3 visits within 50 m of the registered site
On the ground
Structural walls
Roofing not started at the last visit
Community
6 reports
Residents say the block is not yet in use

Monitoring visits

Choose a visit to see what community monitors recorded.

Visit 3, 14 Aug 2026 at 10:42 Faces and number plates are blurred in this public copy
Caption by Clara, confirmed by the monitorAI-assisted

Structural walls are visible across the project site. Roofing has not commenced. Construction materials remain visible. Compared with the previous visit, structural development is evident.

Location
Verified, 32 m from site
Coordinates
9.6139° N, 6.5569° E
Recorded by
Monitor NS-12
Original file
Preserved
Fingerprint
sha256 9f2c…41ab
Visible progress at this visitIndicative only. Engineering questions need an expert.
  1. Empty site
  2. Excavation
  3. Foundation
  4. Structural walls
  5. Roofing
  6. Finishing
  7. Completed facility

Signboard and records

Clara read the project signboard photographed on 14 Aug 2026 and compared it with the budget and procurement records.

FieldOn the signboardIn the recordsResult
Project titleConstruction of 2 classroom blockConstruction of 2-classroom blockMatches
Implemented by[Institution][Institution]Matches
Contractor[Contractor name]Not yet publishedCannot compare
Contract sum₦36,750,000₦36,750,000 allocatedMatches
CommencementFebruary 2025February 2025Matches
CompletionMarch 2026December 2025Differs: review

Differences go to human review. They can have ordinary explanations, such as an approved extension.

Community reports

6 reports, latest 2 shown

“The pupils in Primary 4 and 5 still learn under the neem tree. We were told the block would be ready after the last dry season.”

Voice report, 16 Aug 2026. Transcribed by Clara and checked by a moderator.

“Work stopped when the rains started in June. The blocks and sand are still on site.”

Text report, 2 Aug 2026.

Ground Truth Score

6 of 8 checksModerate confidence

Measures how strong the evidence is, never whether anyone did wrong. A low score means more verification is needed.

  • Verified coordinatesMet
  • Recent monitoring evidenceMet
  • More than one field visitMet
  • Project identity confirmedMet
  • Clear, usable evidenceMet
  • Community confirmationMet
  • Procurement information availableMissing
  • Consistent across recordsMissing

Accountability Signals

2 raised

Signals are prompts to look closer, not findings or accusations.

Timeline signal

Expected completion was December 2025. At the latest visit, roofing had not started.

Signboard signal

The signboard gives March 2026 for completion. The budget record says December 2025.

[Institution] has been invited to respond on this page.

Institutional response

  1. Evidence documented12 Aug 2026
  2. Project Evidence Brief sent20 Aug 2026, to [Institution]
  3. Awaiting responseNo response recorded yet
  4. Clarified or resolved

Ask Clara about this project