“The pupils in Primary 4 and 5 still learn under the neem tree. We were told the block would be ready after the last dry season.”
Voice report, 16 Aug 2026. Transcribed by Clara and checked by a moderator.Construction of 2-classroom block
- Budgeted
- ₦36,750,000
- 2025 capital budget, education sector
- Implemented by
- [Institution]
- As named in the budget record
- Contract
- Not yet public
- Award documents requested
- Location
- Verified
- 3 visits within 50 m of the registered site
- On the ground
- Structural walls
- Roofing not started at the last visit
- Community
- 6 reports
- Residents say the block is not yet in use
Monitoring visits
Choose a visit to see what community monitors recorded.
A foundation slab is visible across the marked site. Blockwork has not started. Sand and blocks are stacked nearby.
Blockwork has risen above window-sill height on all sides, with the door opening in place. Scaffolding is up. Compared with the previous visit, walls have been started.
Structural walls are visible across the project site. Roofing has not commenced. Construction materials remain visible. Compared with the previous visit, structural development is evident.
- Empty site
- Excavation
- Foundation
- Structural walls
- Roofing
- Finishing
- Completed facility
Signboard and records
Clara read the project signboard photographed on 14 Aug 2026 and compared it with the budget and procurement records.
| Field | On the signboard | In the records | Result |
|---|---|---|---|
| Project title | Construction of 2 classroom block | Construction of 2-classroom block | Matches |
| Implemented by | [Institution] | [Institution] | Matches |
| Contractor | [Contractor name] | Not yet published | Cannot compare |
| Contract sum | ₦36,750,000 | ₦36,750,000 allocated | Matches |
| Commencement | February 2025 | February 2025 | Matches |
| Completion | March 2026 | December 2025 | Differs: review |
Differences go to human review. They can have ordinary explanations, such as an approved extension.
Community reports
6 reports, latest 2 shown“Work stopped when the rains started in June. The blocks and sand are still on site.”
Text report, 2 Aug 2026.Ground Truth Score
Measures how strong the evidence is, never whether anyone did wrong. A low score means more verification is needed.
- Verified coordinatesMet
- Recent monitoring evidenceMet
- More than one field visitMet
- Project identity confirmedMet
- Clear, usable evidenceMet
- Community confirmationMet
- Procurement information availableMissing
- Consistent across recordsMissing
Accountability Signals
2 raisedSignals are prompts to look closer, not findings or accusations.
Expected completion was December 2025. At the latest visit, roofing had not started.
The signboard gives March 2026 for completion. The budget record says December 2025.
[Institution] has been invited to respond on this page.
Institutional response
- Evidence documented12 Aug 2026
- Project Evidence Brief sent20 Aug 2026, to [Institution]
- Awaiting responseNo response recorded yet
- Clarified or resolved